ASSEMBLY

Fit the side panels, hood and top grid
onto the appliance. Instructions for
this are enclosed with the panel pack.

Replace any internal parts previously
removed.

PRE LIGHTING

CHECK

Before initial lighting check the
following points:

1. The bottom grate bars must all be
fitted and should move freely and
easily when the riddling mechanism is
operated.

2. The plates round the sides and

back of the grate must be in position
and sitting correctly.

3. The throat plate must be fitted in
the roof of the appliance.

COMMISSIONING

On completion of the installation and
after allowing a suitable period of
time for the fire cement and mortar to
dry out, the fire should be lit and
checked to ensure that smoke and
fumes are taken from the appliance
up the chimney and emitted safely.
Also check all joints and seals.

The central heating pump should be
adjusted to give the correct water
flow against the circuit resistance and
the system should be correctly
balanced.

On completion of the installation and
commissioning please leave the
operating instructions with the
customer and advise on the use of the
fire and any controls on the system.

FREESTANDING KIT

A freestanding kit is available.
Details of dimensions and outputs are
available on request.

150°

Vermiculite
Infill

Flaunching

Take Flue Pipe
Up To Narrowest
Part Of Chimney.

Part No. 010/AV12

150° Elbow

Fig. 10. Typical Installation

Thermostat Flap

LockingNut

18mm

Fig. 11. Thermostat Setting

Page 10

LA30iB 3.99

Advertising