3.8. START SEQUENCE

When the Control Box

ON/OFF switch is set to

the

ON position, it checks all pre-purge safety

switches to ensure they are closed. These

switches include:

Safety Shut-Off Valve Proof of Closure

(POC) switch

Low Water Level switch

High Water Temperature switch

High Gas Pressure switch

Low Gas Pressure switch

If all of the above switches are closed, the

READY light above the ON/OFF switch will light

and the unit will be in the Standby mode.

When there is a demand for heat (hot water), the

following events will occur:

NOTE:

If any of the Pre-Purge safety device switches

are open, the appropriate fault message will be

displayed. Also, the appropriate fault messages

will be displayed throughout the start sequence,

if the required conditions are not observed.

1. The

DEMAND LED status indicator will light.

2. The unit checks to ensure that the proof of

closure switch in the Safety Shut-Off Valve

(SSOV) is closed (Figure 3-3).

Figure 3-3.

Safety Shut-Off Valve

3. With all required safety switches closed, a

purge cycle will be initiated and the following

events will occur:
(a) Blower relay energizes and turns on

blower.

(b) Air/Fuel Valve rotates to the full-open

purge position and closes the purge

position switch. The dial on the Air/Fuel

Valve (Figure 3-4) will read 100 to

indicate that the valve is full-open

(100%).

STEPPER

MOTOR

DETAIL "A"

DIAL

(DETAIL “A”)

100

B

LO

W

E

R

B

U

R

N

E

R

Figure 3-4.

Air/Fuel Valve In Purge Position

4. The blower proof switch (Figure 3-5) closes;

the display shows Purging

and indicates the

elapsed time of the purge cycle in seconds.