To Activate:
Lift & flip the switch to the “ON” position
Verify: The Green “ON” light flashes 1 sec on, 4 sec off
Self Test: Lift & flip the switch from “OFF” to “ARM” position.
Verify: The Green “ON” light must illuminate for 4 sec

then extinguishes. Wait for an additional 21 sec.

Pass: The Green “ON” light must remain extinguished
Fail: The Green “ON” light flashes. Please see Operation

Manual for detail fault code analysis

This satellite ELT only floats w/ floating collar

””” WARNING ”””

FOR AVIATION EMERGENCY USE ONLY.

UNLICENSED OPERATION UNLAWFUL





LITHIUM BATTERY PACK – NON-RECHARGEABLE

P/N 4500010 -1 FOR USE ON Model AK-451-(AF)(AP)(S)
RTCA DO-160E Environmental Categories
F1XB(227)(227)(227)XXXXXXXXXXXXXXXXXX

Replace battery pack
after one culmulative hour
of use or by date shown:
*Battery type: Lithium LiMn02



Replace Main Batteries

By Date: _________

”””

WARNING

”””

USE ONLY DURING SITUATIONS OF GRAVE

AND IMMINENT DANGER!

NEVER CHARGE, SHORT CIRCUIT, PUNCTURE,

DEFORM, INCINERATE, OR OPEN. DO NOT

SUBMERGE IN WATER OR HEAT ABOVE 85

O

C.

REMOVE WHEN DISCHARGED

26

SECTION III

INSTRUCTIONS FOR CONTINUED AIRWORTHINESS (ICA):



3.1

PERIODIC MAINTENANCE (INSTRUCTIONS FOR CONTINUED
AIRWORTHINESS):


REFERENCES
: FAR Part 91.52, Part 91.169, Part 43 Appendix D (i).

FAR Part 91.207 Paragraph (d)
FAR Part 91.407 Appendix D (i)


PURPOSE:
To insure continued reliability of your ELT, it must be inspected for damage and wear
which could be caused by age, exposed elements, vibrations, etc. Even the best
designed equipment, if not properly maintained and cared for, will eventually fail.

IMPORTANT NOTES:
The following inspections must be performed, a minimum of one time every year:

3.1.1

Secure Inspection: Inspect the ELT Main Unit and Mounting Tray to insure
all fasteners and mechanical assemblies are secure.


3.1.2

Corrosion Inspection for Coaxial Cable: Inspect the Coaxial Cable

connecting the ELT Main Unit to the Antenna for cuts or abrasions on its outer jacket.
Disconnect the BNC connectors on each end. Examine both the BNC connectors and
the mating plug on the Antenna and the ELT Main Unit for any signs of corrosion.

3.1.3

Corrosion Inspection for Remote Wiring Modular Cable: Inspect the

Remote Wiring Modular Cable, connecting the ELT Main Unit to the Remote Unit of
signs of wear or abrasion on its outer jacket. Remove the Modular Connecting Cable
and inspect and jack and plug assembly for corrosion.

3.1.4

Expiration Date Check: Check the expiration date of the ELT Main Unit

and the Remote Unit Batteries. Replace if necessary.

3.1.5

Battery Leakage Check: Disassemble the ELT to inspect the Battery

Compartment for signs of corrosion or battery leakage. If any battery leakage is
present, the battery Assembly must be replaced. The Battery useful life is 5 years.

3.1.6

Operational Test: After completing the above inspections, a Functional Test

as described in Paragraph 2.3 must be performed to verify proper operation.

3.1.7.1 G-Switch Check: Ensure that the Main Switch on the ELT main unit must
be selected at “ARM: position at all times. Activate the ELT using applied force. The
direction for mounting and force activation is indicated on the ELT. The AK-451-
(AF)(AP) ELT can be activated by using a rapid forward (throwing) motion coupled

Advertising