Vrla – C&D Technologies 41-6976  RB VRLA Rack User Manual

Page 7

Advertising
background image





Page 7 of 9

VRLA



R-1. Receive and inspect rack components


Upon receipt of the RB Rack materials, inspect and document any damage to these materials. Damage
claims must be filed promptly with the carrier.

R-2. Review drawings and instructions

R-3. Verify Parts Received Against Bill of Materials


Before assembly, verify that all rack materials are present against the detailed bill of materials shown on the RB
Rack Assembly Drawing (RB_ _TEQ).

R-4. Get safety equipment and tools to rack installation location


Safety equipment as described on page 1 of this publication.

Tools - The following items will assist you to properly install RB Rack retrofit materials.

Insulated tools are strongly recommended for safety purposes.

9/16” Socket wrench

Torque wrench to 46ft-lbs

Tape measure

9/16” Open-end wrench

Needle nose pliers

Knife

R-5. Anchoring


It is very important that the rack is securely anchored to the floor using ALL four 15/16” diameter mounting
holes provided in the rack’s base.

It is the responsibility of the installer to verify that the rack is anchored in accordance with allowable floor
loading, applicable codes and regulations. Under normal conditions, this should have been done with the initial
installation of the rack. If not, it needs to be done prior to performing the following procedures.

Contact C&D Technologies @

1-800-543-8630

VRLA RB Battery Rack Retrofit - Task Flow Chart

Verify rack is properly
anchored

Install spacer blocks

and end braces

Install hold down strut
and KYDEX insulator

Review drawings &
instructions

Verify retrofit items
received against Bill
of Materials

Get safety equipment

and tools to rack

location

Receive and inspect

retrofit components

Check installed
cables for adequate
clearance

Install hold down rod

Install top cover

Verify proper torque

of all connecting

hardware

START

QUESTIONS ?

Advertising