Special attention should be paid to clearances

between the front of the boiler and the closet door

when it is closed.

Consult the American National Standard Z21.13 for

more information concerning closet installations. In

Canada, refer to the latest edition of CSA-B149.1.

Figure 2JVS. Closet Installation

Dimensions in inches cm.

6 15

6 15

6 15

4*

10

*6" for models JV160 to JV225.

width and depth of the heater by at least 12 inches

(305mm) in all directions. The masonry must be laid

with ends unsealed, and joints matched to provide

free circulation of air from side to side through the

masonry (see Figure 1). If the boiler is installed in a

carpeted alcove, the entire floor of the alcove must be

covered by a noncombustible platform.

2E. Clearance / Closet Installations

All Mini-Therm JV's can be installed in a closet as

long as the minimum clearances are observed.

See

Table 2JVH and Figure 2JVH for

clearances required for the Mini-Therm JVH.

See

Table 2JVS and Figure 2JVS for

clearances required for the Mini-Therm JVS

Figure 2JVH. Closet Installation.

TOP

VIEW

SIDE

VIEW

2

(51)

A

2

(51)

5

(127)

6

(152)

6

(152)

MIN

Dimensions in

inches (mm).

Air

Openings

B

Note: Clearances listed are manufacturer’s tested values. These are given as minimum values. Where local and national

codes apply, and values are different than those listed use the greater value to ensure safe operation.

Minimum Boiler Clearances from Combustible Surfaces.

Dégagements Minimaux à Assurer Entre Ics Parois de L’appareil et leo Constructions Combustibles

Boiler Sizes

50 - 225

Clearances

in cm

Left side

2 5

Right side

5 15

Rear

2 5

Front

4 10

Flue

(using B-vent)

6 15

Top

23 58

Boiler Sizes

50 - 125

160 - 225

Clearances

in cm

in cm

Left side

6 15

6 15

Right side

6 15

6 15

Rear

6 15

6 15

Front

4 10

4 10

Flue

6 15

6 15

Top

23 58

36 91

Table 2JVS Minimum Boiler Clearances

Table 2JVH Minimum Boiler Clearances