6 electrical installation – NORAC UC4+BC+OM1 User Manual

Page 17

Advertising
background image

14

4.6 E

LECTRICAL

I

NSTALLATION

Figure 14 – Cables: C02, C02B and C03

1. Route the 4491BC cable from the hitch,

following existing hose and cables, to
the back of the sprayer near the valve
block. Connect the 4491BC DIN
connectors to the proportional valves.
Connect the four free-hanging wires on
the 4491BC cable to the foam marker
solenoids.

2. Connect the CAN Node cable (C02B) to

the 4-pin AMP plug on the 4491BC
cable (Figure 14).

3. Route the CAN Node cable (C02B) to

the roll sensors and connect to the
sensors. Follow existing cables and/or
hydraulic lines.

4. For the OM2 kit:

Connect the severe terrain cable
(C03) to C02B. Connect the inner
wing sensors to C03. Connect the
sensor branch cable (C02) to the 4-
pin AMP plug on C03.

5. For the OM1 kit:

Connect the sensor branch cable
(C02) to the 4-pin AMP plug on
C02B.

6. Route the sensor branch cable (C02) to

the outer wing and main sensors and
connect to the sensors. Follow existing
cables and/or hydraulic lines along the
boom.

7. Cable-tie the installed cables every 12

inches.

IMPORTANT:

Provide enough slack in all cables to
account for the movement of the main
section, parallel lift, and FOLDING boom
movement.

Advertising