NORAC UC4+BC+SM4 User Manual

Page 25

Advertising
background image

22

11. Route the DT connectors on C16 to

the Summers valve block.

12. Disconnect the Left tip lift DT

connector from the Summers valve
block and plug it into the connector
marked “ROLL CW” on cable C16.

13. Connect the DT plug labeled “ROLL

CW” on cable C16 into the Left Up

connector on the Summers valve block.

14. Disconnect the Right tip lift DT

connector from the Summers valve
block and plug it into the connector
marked “Roll CCW” on cable C16.

15. Connect the DT plug labeled “ROLL

CCW” on cable C16 into the Right Up
connector on the Summers valve block.

16. Connect the Main Lift interface cable

(C13) to the 3 pin tower on cable C11.

17. Route the DT connectors on cable C13

to the Summers valve block.

18. Remove the connector from solenoid H

on the Summers valve and connect the
DT plug on cable C13 to the valve.

19. Connect the plug that was disconnected

from solenoid H to the receptacle on
cable C13.

20. Connect the plug (P01) to the 6 pin

tower on cable C11.

21. Connect the CAN Node cable (C02B)

to the 4-pin AMP plug on C11.

22. Route the CAN Node cable (C02B) to

the roll sensors. Follow existing cables
and/or hydraulic lines.

23. Connect the extension cable C06 to

the CAN Node cable.

Cable C06 should only be

required on 132’ booms.

24. Connect the sensor branch cable (C02)

to the 4-pin AMP plug on C14.

25. Route the sensor branch cable (C02) to

the wing and main sensors. Follow
existing cables and/or hydraulic lines
along the boom.

26. Cable-tie the installed cables every 12

inches.

IMPORTANT:

Provide enough slack in all cables to
account for the movement of the

main section, parallel lift, and
FOLDING boom movement.

Advertising