ROGUE TERRAIN OFF GRID POWER SUPPLY ENCLOSURE

5

POWER WIRING TEST
Replace the Load fuse in the Load fuseholder .
Replace the Solar fuse in the Solar fuseholder .
Replace the Battery fuse in the Battery fuseholder .
With a multimeter set to a voltage scale that will accommodate 12 VDC,

measure the voltage across the bottom screws of the Battery (+) and Battery

(-) terminals . Then measure the voltage across the Battery and Ground

terminals on the green connector on the left side of the charge controller . The

voltage levels should be the same .
With a multimeter set to a voltage scale that will accommodate 20 VDC,

measure the voltage across the bottom screws of the Solar (+) and Solar (-)

terminals . Then measure the voltage across the IN (+) and Ground (Solar

input) terminals on the green connector on the right side of the charge

controller . The voltage levels should be the same .
Ensure that the Low Voltage Disconnect (LVD) device, if used, is set to the

“On” position . With a multimeter set to a voltage scale that will accommodate

12 VDC, measure the voltage across the bottom screws of the Load (+) and

Load (-) terminals . Then measure the voltage across the bottom screws of the

Battery (+) and Battery (-) terminals . The voltage levels should be the same .
Set the LVD device to the desired low voltage disconnect level .
The Rogue Terrain packaged charge controller is now functional .