Installation and Instructions

13

Electrical Junction Box

Wiring should be connected at a customer

provided junction box, outside the firebox, prior to the
installation of the blower kit.

Electrical Services

If an electrical supply of 120V is being roughed in

to the fireplace junction box to provide for future
installation of the optional blower kit, the wiring should
be connected to the junction box.

NOTE: All electrical connections (Fig. 12) are to

be made in accordance with CSA Standard C22.1
Canadian Electrical Code part 1 or with the National
Electrical Code, ANSI/NFPA 70 (latest edition) and/or
in accordance with local codes.

Install Optional Blower/Fan Kit – BL102

NOTE: A FEW BASIC SAFETY RULES BEFORE

YOU START:

1. Make sure you have and are using/wearing proper

personal safety devices such as but not limited to
gloves, safety eye glasses/eye protection .

2. Check to ensure that electrical service has been

provided to the junction box located in the bottom
chamber of the firebox.

3. Check local building codes before installation of the

firebox and blower kit.

4. All wiring must be installed and/or inspected as

necessary to comply with the local authority
having jurisdiction.

5. The circuit breaker controlling the power supply to

the pre-wired junction box in the appliance must be
in the off position before beginning installation of
the blower .

6. The appliance, when installed, must be electrically

grounded in accordance with local codes or – in
the absence of local codes – with the National
Electrical Code, ANSI/NFPA 70 or the Canadian
Electrical Code, CSA C22.1

M

FIREBOX ENCLOSURE

INSTALLER CONNECT TO

110VAC HOUSE WIRING

PER APPLICABLE

LOCAL CODES

BLOWER MOTOR ACCESSORY

SPST BLOWER SWITCH

STEEL HANDI-BOX

W/SINGLE GANG

RECEPTACLE

VFBC WIRING DIAGRAM - ALL SIZES

Fig. 12