INSTALLATION

(continued)

1--3

Functional Test

The Functional Test consists of three checks: manual

operation, voltage checks, and electrical operation.

Do these checks in the order presented to

avoid damaging the automatic transfer switch.

!

Read all instructions on the Wiring Diagram and labels
affixed to the automatic transfer switch. Note the control

features that are provided and review their operation

before proceeding.

1 – Manual Operation Test

A detachable manual operator handle is provided on the
Transfer Switch for maintenance purposes only. Manual

operation of the transfer switch should be checked before

it is energized (operated electrically).

Do not manually operate the transfer switch

until both power sources are disconnected:

open both circuit breakers.

!

1. Insert the maintenance handle into the hole in the

shaft, left side of the operator.

2. Move the maintenance handle as shown to manually

operate the transfer switch. The switch should operate
smoothly without any binding. If it does not, check for

shipping damage or construction debris.

3. Return the transfer switch to the N (normal) position.

4. Remove the maintenance handle and store it on the

transfer switch in the place provided.

Verify that the maintenance handle has

been removed before proceeding!

!

Now continue to 2 – Voltage Checks on next page.

maintenance

handle

shaft

hole

Figure 1-4. Removable maintenance handle on

260 and 400 amp. E–design transfer switches.