General, Dielectric test, Operational test procedure – Basler Electric BE1-50/51B-122 User Manual

Page 41: Test equipment required, Section 5, Testing -1, General -1, Dielectric test -1, Operational test procedure -1, Test equipment required -1

Advertising
background image

SECTION 5

TESTING

GENERAL

Dielectric testing, operational testing, and periodic testing are described in the following paragraphs.

DIELECTRIC TEST

In accordance with IEC 255-5 and IEEE C37.90-1989, one-minute dielectric (high potential) tests may be
performed as follows:

All circuits to ground:

2,828 Vdc or 2,000 Vac

Input to output circuits:

2,828 Vdc or 2,000 Vac

Output contacts are surge protected.

OPERATIONAL TEST PROCEDURE

The following procedures verify operation of relays BE1-50/51B-219 (5 ampere model) and BE1-50/51B-
226 (1 ampere model). The test setup of Figures 5-1 and 5-2 are intended primarily as an illustration of
the principles involved. Other test setups known to be capable of testing with the stated and implied
tolerances (including equipment specifically designed for testing relays) may be used.

Test Equipment Required

 Current source with a range from 0 to 20 Aac (sensing input current)
 AC or DC voltage source (target operation)
 Timer or counter

CAUTION

To ensure proper timing during testing, before each test, remove the current from
the unit for R times D seconds (refer to Section 1, Specifications, Time Reset for
R and D definitions).

9252000981 Rev H

BE1-50/51B-219/-226 Testing

5-1