Lifting of the Machine Framework

Notice: Make sure not to allow the frame to collide with the structures under

construction in hoisting the frame, especially when the frame has been set on the tank
wall, but to use the top wheels of the frame at front and rear to hold against the tank
wall, instead of making the tank wall collide with the frame;
The hoisting rope can be loosened only when both the drive wheel and driven wheel
of transverse walk frame have been set on the wallboard.

The angular separation formed between the hoisting ropes is no less than 60°. During
the hoisting, pull out the bolt, rotate the top wheel 90°and pull back the bolt making
the top wheel surface vertical to the ground level (to make sure that the track
supporting wheel will not collide with the tank wall during hoisting) . After that, set
down all the traveling wheels of the frame on the tank wall. Pull out the bolt of the
flexible top wheel after finishing hoisting, rotate the top wheel 90°, pull back the bolt
making the top wheel surface parallel to the ground level, and take back the flexible
top wheel.

4.3 Operation Instructions

Security Notices
The equipment operation is forbidden before reading through operation instructions in
this manual.

警告

Beware of electric shock

●Exposed skin or moist clothing is forbidden to contact these charged parts.
● Make sure that you are insulated with the work-piece and the ground.