6.2.6.3 UTILITY: SWITCH-ID

EDIT SWITCH ID:
**CRS-300 TEST MESSAGE**

To edit the Switch ID string: Use the

◄ ► arrow keys to select the cursor position on the

bottom line, and then use the arrow keys to edit the character in that position. You may

use the following characters:

[space] ( ) * + - , . / 0 through 9 and A through Z

A maximum of 24 characters are allowed. Press [ENT] when done.

6.2.6.4 UTILITY: TEST

This is an excellent method to test the whole system before setting the Switch for automatic

mode.

Once you select this screen, the Switch suspends normal system polling and initiates a test:

CONFIG TESTING.......2
TM#: 1 OK

TEST COMPLETE.
CHECK 2.

The total configuration of each activated modem is configured into the Redundant Modem in

sequence. If any configuration is not accepted, a fault will be shown on the display.

Press [ENT] or [CLR] to return to the top-level (main) menu.

6.2.6.5 UTILITY: RELAY

POWER-OFF RELAY LOGIC:
DEFAULT INVERT (ENT)

The alarm relay condition terms “Normally Open” and “Normally Closed” are easily

misinterpreted. To facilitate customer connection to existing external equipment, you may use

this menu to invert the logic of the external relay condition.

Use the

◄ ► arrow keys to select DEFAULT or INVERT, and then press [ENT].