Apply mains voltage to the test station.

Commissioning

Before commissioning please check:

Are the measuring electrodes /temperature sensors wired in accordance with the wiring diagram?

Checking wiring

Applying mains voltage

Maintenance

If faults occur that are not listed above or cannot be corrected, please contact our service centre or

authorized agency in your country.

Danger

When loosening the measuring electrode steam or hot water might escape.

This presents the danger of severe scaling. It is therefore essential not to remove the

electrode unless the boiler pressure is verified to be zero.
The electrode is hot during operation. This presents the danger of severe burns to hands

and arms. Installation and maintenance work should only be carried out when the system

is cold.

We recommend to remove the measuring electrodes every 6 months and clean them with a wet cloth.

Maintenance interval