13036 Probe Conditioning System

INSTALLATION

Location

The compact JIC box is provided with flanges, each having two 1/4" mounting holes. Locate the
box within about 6 feet of the sensor, if possible. Avoid locations close to a source of
combustibles such as a natural gas fitting that could develop a leak. Wire and pipe the system as
shown in Fig. 1. The controller will hold the additive gas flow constant during burnoff and
purge/delay periods.

Commissioning

Locate the reheat well and probe in the generator wall so that the indicated probe temperature is

stable between 1450 and 1650oF.
With the power switch on, set the reference airflow rate close to full scale (2cfh).
Initiate a burnoff routine in the control instrument with a nominal burnoff time of 3 minutes.
Adjust the burnoff airflow rate to 3cfh and observe the probe millivolt reading. If it doesn't drop
well below 200mv (preferably to zero) before the burnoff is complete, increase the flow rate or
the time until it does. Your system is now operational.
Values of 24 hours cycle time, 3 minutes burnoff time and 3cfh burnoff flow are typical for this

application. When operating at dew points lower than 35oF, it may be desirable to reduce the
cycle time to 12 hours or less. If you encounter difficulties, contact SSI for advice and assistance.

OPERATION

See Fig. 1 for a brief explanation of the routine and refer to the GOLD PROBETM instruction
manual for a more complete discussion of probe conditioning.

THANK YOU

We think you will be delighted with the performance of your probes once you have installed this
engineered conditioning system. If you have any questions, suggestions or problems, your

GOLD PROBETM team is only as far as your phone. Call us at 1-800-666-4330. We listen.
And we respond.

PROBE CONDITIONING SYSTEM MANUAL