Phase 5 – preparation of counter-wall – MCZ Mondrian User Manual

Page 11

Advertising
background image

INSTALLATION AND USE MANUAL

Chapter 3

MONDRIAN

page

11

Chapter 3

Technical service – all rights reserved by mcz spa

Reproduction prohibited

3.6. PHASE 5 – PREPARATION OF COUNTER-WALL

Prepare the wall for recessed installation using fireproof material (for example, fireproof plasterboard). Provide

an opening of 660X623 mm, 230 mm from the floor (see drawing). It is advisable to add a flat sheet of steel (the

material as the plasterboard uprights) on the inside to fasten the steel frame support (element 5). Align the

sheet with the opening and at a height of 95÷105 cm from the floor (see phase 6).

23

0

623

660

PARETE

A FILO

=

=


Position the wall with the opening aligned with the fireplace stove and flush with sides, lower edge and upper

edge.

Advertising