Note: Diagram intended as guide only.

Satellite-fill icemaker installation procedure

Install icemaker and rough-in utilities without optional slide-out accessory

The requirements below are for icemaker installation without the Follett slide-out accessory. These procedures
ensure that the icemaker can be easily removed as one unit for cleaning and maintenance. For installation
with the slide-out accessory, refer to instructions to install icemaker and rough-in utilities with optional slide-out
accessory.

General requirements

Front of icemaker free of obstructions, plumbing lines, electric conduits.

305mm (12") minimum clearance above icemaker for access to icemaker components.

153mm (6") minimum clearance between exhaust side of icemaker and adjacent equipment.

Do NOT weld icemaker to counter channels.

Large, removable panels in counter face to allow icemaker removal.

Machine stand accessory required for icemakers not supported on counter channels.

Connection requirements

Compression fittings for water and drain lines.

Separate drains for condenser and icemaker. Do NOT connect drains.

Power supply with 6 feet.

bin signal from
dispenser
to icemaker

water shut off

compression fittings
for water and drain lines

separate power
to icemaker

separate power
to dispenser

305mm

(12")

clearance

front of
icemaker
clear

Advertising