Faria Instruments GW0016 User Manual

Page 10

Advertising
background image

Page 9

Faria

®

Serial Bus Installation and Wiring Guide

The system consists of:
• One Gateway box to interface with the engine and external senders and sensors.
• One 4” Tachometer with Fuel Monitor
• Various 2” instruments, including but not limited to

• Voltmeter
• Oil Pressure gauge
• Engine Temperature gauge
• Fuel Level gauge
• Transmission Temperature

Installation
Installation of the Fari

®

Serial Bus system is accomplished as follows:

Gateway Box
The Gateway

box is the central unit of the system. As all of the senders and other

information source peripherals connect to the Gateway

™,

the Gateway

box should be

mounted in a protected area in the best location to provide the maximum cabling benefit.

The Gateway

box power cable must be installed to allow connection to “battery positive”

(always on), “battery negative” (ground), and a source of “switched power” which turns on
with the engine ignition switch (see Figure 2 and Table 1).

The “Faria

®

Bus” cable must be routed from the Gateway

box to the instrument panel area

to connect the instruments to the data bus and instrument power (see Figure 3).

The remainder of the connections to the Gateway

box are described below.

Instruments
The instruments are mounted using the provided back-clamps and mounting hardware.
Each instrument comes with a bus connection cable (12”). The main “Faria

®

Bus” cable

from the Gateway

box is connected to the most convenient instrument using either of the

two four (4) pin connectors provided on the instrument case.

Each additional instrument is connected to the previous instrument using one of the 12” bus
connection cables. The cable may be connected to either of the two connectors provided on
the instrument case (see Figure 3).

Advertising