[4] Contents Of The Duct Smoke Detector Kit
1. Complete housing base and cover assembly
2. Two #10×1

1

4

″ sheet metal screws for mounting

3. Two sampling tube filters
4. One test magnet
5. Drilling template
6. Two foam gaskets
7. Four #6-self tapping mounting screws for the metal

sampling tube and optional exhaust tube extension

8. One inlet tube end plug
9. One plastic sampling tube
10. One #8 self-tapping screw for the plastic sampling tube
NOTE: For ducts over 1

1

2

feet, longer inlet sampling tubes

must be ordered to complete the installation. They
must be the correct length for the width of the duct
where they will be installed. See Table 1 on page
3 to determine the inlet tube required for different
duct widths.

[5] Installation Sequence
[5.1] Verify Duct Air Flow Direction And Velocity
Model DH100ACDCP detectors are designed to be used in
air handling systems having air velocities of 500 to 4000
feet per minute. Be sure to check engineering specifications
to ensure that the air velocity in the duct falls within these
parameters. If necessary, use a velocity meter to check the
air velocity in the duct.

[5.2] Drill The Mounting Holes
Remove the paper backing from the mounting template
supplied. Affix the template to the duct at the desired
mounting location. Make sure the template lies flat and
smooth on the duct. Center punch holes A and B. Drill the
holes as indicated on the template.

[5.2.1] Sampling Tube Installation for Ducts Less
Than 1

1

2

Feet Wide (see Figure 2)

1. Remove the front cover.
2. Slide the plastic sampling tube into the housing bushing.
3. Align the holes in the bushing with the holes in the

sampling tube. Make sure there are 6 exposed holes on
the plastic sampling tube. Secure with the #8 self-tapping
screw into the bottom of the permanent tube (shown in
Fig. 1).

NOTE: For ducts greater than 1

1

2

feet in width, refer to

sections [5.4.1] and [5.4.2].

Figure 2. Plastic sampling tube
connected to duct smoke detector:

[5.3] Secure The Detector Housing To The Duct
Slide the foam gaskets over the tube bushings as shown in
Figure 3. Use the two 1

1

4

″ long sheet metal screws to screw

the detector housing to the duct.
CAUTION: Do not overtighten the screws.

D100-68-00 2 I56-1147-12R

[3] Figure 1. Exploded View Of Duct Smoke Detector Components:

FOAM

GASKETS

PLASTIC

SAMPLING TUBE

CONDUIT HOLES

DETECTOR

HOUSING

TERMINAL STRIP

DETECTOR

COVER

SAMPLING TUBE

FILTERS

COVER MOUNTING

SCREWS

PLASTIC SAMPLING TUBE

SELF-TAPPING SCREW

POWER BOARD

DETECTOR BOARD

Advertising