8. Preparations Before Operation

Check the following items before starting operation:

①

Visually inspect the UPS to verify that there is no visible damage.

②

Check that the UPS is connected to a utility power source that meets the input

specifications.

③

Check that the input breaker MAIN MCCB is set to “OFF”.

④

Check that load devices are connected correctly.

⑤

Check that none of the cable connections is loose.
















②

, ⑤Check input

power source

④

, ⑤Check load

connections.

③

Breaker is “OFF”.

※

This figure shows E11A202U001.