Setting up back-to-back operation, Changing operating mode – Paradyne 9820-2M User Manual

Page 48

Advertising
background image

Configuration Options

4-12

9820-A2-GB20-20

June 2000

5. Select the

Delete EDLCI Connections and Make a Mgmt Only

PVC

option.

PVC connections for the selected DLCI are broken, the Port-1 DLCI mapped
to this network DLCI and the embedded management DLCI (EDLCI) are
deleted, and the selected DLCI will be reconfigured as a management PVC
using the Node IP Address.

See Table 4-8,

DLCI Record Options

, for configuration information.

Setting Up Back-to-Back Operation

Using this special feature, you can set up two FrameSaver units that are
connected back-to-back without frame relay switches between them, as in a
test bench setup.

Changing Operating Mode

When setting up back-to-back operation:

H

One unit must be configured for Standard operation, which is the setting for
normal operation.

H

The other unit must be configured for Back-to-Back operation so it presents
the network side of the UNI (user-network interface).

Only one of the units will have its operating mode changed.

"

Procedure

To set up back-to-back operation:

1. On the unit to be configured for Back-to-Back operation, manually configure

DLCIs; DLCIs should be configured before connecting the two units.

2. Access the Change Operating Mode screen.

Main Menu

Control

Change Operating Mode

3. Select Back-to-Back Operation, and respond Yes to the

Are you sure?

prompt.

4. Save the change.

"

Procedure

To return the unit to normal operation:

1. Return to the Change Operating Mode screen and switch back to Standard

Operation.

2. Respond Yes to the prompt and save the change. The units can be

reconnected to a standard frame relay network.

Advertising