IMPORTANT

The vent system must terminate so that proper clearances are maintained

as cited in local codes or the current editions of the National Fuel Gas Code,

ANSI Z223.1/NFPA 54.

Do not terminate the exhaust vent terminal over public area where condensate

or vapor can cause nuisance or hazard.

Plan the vent system layout so that proper clearances are maintained from

plumbing and wiring.

Vent pipes serving power vented appliances are classified by building codes

as "vent connectors". Required clearances from combustible materials must

be provided in accordance with information in this manual under LOCATION

OF HEATER and CLEARANCES, and with National Fuel Gas Code and

local Codes.

IMPORTANT

Plan the layout of the vent system backwards from the vent termination to

the appliance.

WARNING

USE ONLY THE VENT TERMINALS SUPPLIED WITH THIS UNIT.

TERMINATION OF A VENT SYSTEM WITH A DEVICE OTHER THAN

THE SUPPLIED VENT TERMINATIONS WILL AFFECT SYSTEM

PERFORMANCE AND RESULT IN A SAFETY HAZARD.

DIRECT VENTING

The air intake provided on the unit contains a mesh screen (see Figure 7)

to prevent large particles from entering the unit.

FIGURE 7.

WARNING

WHEN THE UNIT IS TO BE SETUP AS A DIRECT VENT, THE MESH

SCREEN MUST BE REMOVED. THE INLET VENT PIPE MAY THEN BE

GLUED TO THE AIR INTAKE (see Figure 8) PROVIDED ON THE UNIT.

DIRECT VENT TERMINAL INSTALLATION

IMPORTANT

THIS UNIT CONSISTS OF TWO VENT TERMINALS - AN INTAKE VENT

TERMINAL AND AN EXHAUST VENT TERMINAL. THE INTAKE VENT

TERMINAL IS A 3" 45° PVC ELBOW WITH A DOME MESH WIRE SCREEN

AND THE EXHAUST VENT TERMINAL IS A 3" 45°PVC ELBOW WITH A

MESH WIRE SCREEN.

NOTE: TO PREVENT EXHAUSTING PRODUCTS FROM CIRCULATING TO

THE AIR INTAKE IN WINDY/COLD AREAS, THE MAXIMUM PRACTICAL

DISTANCE BETWEEN THESE TWO TERMINALS IS RECOMMENDED

FIGURE 8.

IMPORTANT

WHEN LOCATING THE TERMINALS ON A SIDEWALL, THE FOLLOWING
SPECIFICATIONS PERTAINING TO TERMINAL LOCATION MUST BE
FOLLOWED.

1. The intake vent terminal and the exhaust vent terminal must terminate on

the same exterior wall and must be located at a minimum of 24" (61cm)

from the vertical centerline of the exhaust vent terminal (see Figure 9). In

colder climates increasing the 24" (61cm) minimum will reduce possibility

of frost over from side winds blowing exhaust vapors to the air intake of

the direct vent.

2. The horizontal centerline of the intake vent terminal may not be located

lower than the horizontal centerline of the exhaust vent terminal
(see Figure 9).

INSTALLATION SEQUENCE

For installations in the City of Los Angeles, California Category IV PVC Pipe
such as that manufactured by Brownline Pipe Company, must be used as
vent pipe material

CAUTION

Vent terminals supplied with the heater must be used.

NOTE: BEFORE BEGINNING INSTALLATION OF ANY VENT PIPE READ

THE VENT PIPE MANUFACTURER'S INSTALLATION INSTRUCTIONS.

1. After the points of termination have been determined, use the cover plates

as templates to mark the holes for the vent pipes to be inserted through

the wall. BEWARE OF CONCEALED WIRING AND PIPING INSIDE OF

WALL.

2. If the vent terminals are being installed on the outside of a finished wall, it

may be easier to mark both the inside and outside wall. Align the holes by

drilling a hole through the center of the template from the inside through

to the outside. The template can now be positioned on the outside wall

using the drilled holes as a centering point for the template.

3. A) MASONRY SIDE WALLS

Chisel an opening approximately 1/2" (1.3 cm) larger than the marked

circle.

B) WOODEN SIDE WALLS

Drill a pilot hole approximately one quarter inch outside of the marked

circle. This pilot hole is used as a starting point for a saws-all or sabre saw

blade. Cut around the marked circle staying approximately one quarter

inch outside of the line. (This will allow the vent pipe to easily slide through

the opening. The resulting gap will be covered by the vent terminal cover

plates.) Repeat this step on the inside wall if necessary.

4. Cut a length of 3" PVC pipe about 3.5" (8.9 cm) longer than the wall

thickness at the opening.