After filling and purging, start the boiler as follows:

❏

Turn the thermostat to its lowest setting so that there is no call for
heat.

❏

Set the limit control as recommended in the Installation Instructions.

❏

Turn on the main electric switch to the boiler.

❏

Set the thermostat above actual room temperature. Check for proper
sequencing of elements. Heat the entire system to about 200°F so that
dissolved air and gases in the system water will be emitted and vented.

❏

Check limit control operation by lowering the
control settings as described in the
“Troubleshooting” section on page 7.

❏

Restore the limit control settings to their
recommended values and set the thermostat to the
desired room temperature.

❏

Fill in “Installation and service certificate” below.

❏

If the boiler operates incorrectly or fails to start,
refer to “Troubleshooting” on page 7.

Boiler model __________________ Series __________ CP number ___________ Date installed _______________

Measured Btuh input ____________

Installer ________________________ ________________________________ ______________________________
(company) (address) (phone)

_____________________________________

(installer’s signature)

Installation and service certificate

❏ Installation instructions have been followed.
❏ Checkout sequence has been performed.
❏ Above information is certified to be correct.
❏ Information received and left with owner/maintenance person.