F. g-switch functional check – item 4, G. performance testing setup – ACR&Artex ME406 ACE ELT User Manual

Page 35

Advertising
background image

25-62-30

Page 35 of 84

May 03/13

ARTEX PRODUCTS / ACR ELECTRONICS, INC

DESCRIPTION, OPERATION, INSTALLATION AND MAINTENANCE MANUAL

ME406 (453-6603), ME406HM (453-6604)

(c)

When the total of all known transmissions exceeds one hour; or

(d)

On or before battery replacement (expiration) date.

SUBTASK 25-62-30-750-001

F.

G-Switch Functional Check – Item 4

CAUTION:

A JUMPER IS REQUIRED TO PERFORM THIS CHECK. DUE TO THE POTENTIAL OF

PHYSICAL DAMAGE IF THE JUMPER IS IMPROPERLY INSTALLED, THIS STEP SHOULD

ONLY BE PERFORMED BY AN EXPERIENCED TECHNICIAN/MECHANIC.

(1)

Reinstall the battery in accordance with SUBTASK 25-62-30-450-001 on page 71.

NOTE: If tests 5a through 5h are going to be performed, the battery may be temporarily

installed with only two screws, located on a diagonal from each other.

(2)

Perform this functional check within the first 5 minutes after the hour (UTC), as required by

AC 43.13-1, Chapter 12, § 12-22, Note 3.

(3)

Notify any nearby control tower of your intentions.

(4)

Install the 500-0079 ME406 G-Switch Loop Test Connector Fixture on the ELT receptacle or

jumper ELT receptacle pins 5 and 12.

NOTE: The ELT cannot be activated using this procedure unless pins 5 and 12 on the ELT

receptacle are jumpered. See Figure 18 Metal Airframe Wiring Diagrams on page 59.

(5)

Verify the ELT switch is in the “ARM” position.

(6)

Monitor 121.5 MHz on an AM receiver.

(7)

Activate the ELT by using a rapid forward (i.e., throwing) motion in the direction of the arrow

on the ELT label, followed by a rapid reversing action.

(8)

Verify activation by listening for the aural sweep tone on the receiver.

(9)

Reset the ELT by toggling the control switch to the “ON” position and then back to the “ARM”

position.

SUBTASK 25-62-30-750-002

G. Performance Testing Setup

NOTE: The ELT software routine logs battery life in 30-second increments. A minimum of 30

seconds is added to the battery usage total each time the ELT is activated and de-activated.

If the ELT is left activated beyond the first 30 seconds, additional time is added in 30-

second increments.

NOTE: Careful planning of the performance tests is necessary to avoid activating the ELT more

than necessary. Plan the performance testing in a manner that allows tests to be run

concurrently and test equipment settings to be quickly switched from one test to another.

By doing so, the three-minute warm-up requirement can be eliminated from a number of

tests and battery run time minimized to a large extent.