Step 1: Determine the location for installation (Make sure all ADA requirements are

met).

***NOTE: The installation of Global Lift Corp’s anchor system’s are a guideline of

minimum requirements. In some states or municipalities they may require additional

steps due to their local codes or ordinances.***

Step 2: Make sure that all the parts are present (Refer to the parts list)

1 - Anchor Sleeve w/ Base

1 - Bonding Lug

1 - Plastic Cap

Step 3: At the determined location for installation, chalk out a 3’ X 3’ area prior to

cutting out the concrete. (Refer to overview, the front end of the Anchor Sleeve

must be 12” to 17” from the water’s edge and 6” deep). New Construction, the

concrete must be 6” deep with a ½” reinforcing rod, minimum of an 18” grid.

NOTE: Make sure that all local codes and ordinances are met.

Step 4: Once the 3’ X 3’ area is cut out, make sure you drill in the inner wall of all 4

sides of the area (refer to the section detail) for the purpose of cold pinning the new

concrete to the old concrete. Use 1/2” rebar, 6” to 8” in length.