1. Set the on/off switch [2] in the ON position. The indicator [1]

blinks.

To execute the test at a slower pace, set the on/off switch in the

S (‘slow’) position. The indicator blinks slower.

2. Insert one end of the cable under test into the socket in the

master: [3] for RJ45, [4] for RJ11/RJ12.

3. Insert the other end of the cable into the socket in the remote

[7] for RJ45, [8] for RJ11/RJ12.

The cable test lights on the master [5] and on the remote [6]

light up in sequence.

4. After testing, remove the cable from master and remote and set

the on/off switch in the OFF position.

5.2

Test results: exam ples

Description

Sequence

Good connection: all indicators

light up in sequence.

Note: Indicator G lights up

only for cables with a ground

(GND).

master:

1 2 3 4 5 6 7 8 G

(8P8C)

remote:

1 2 3 4 5 6 7 8 G

(8P8C)

master:

1 2 3 4 5 6 (6P6C)

remote:

1 2 3 4 5 6 (6P6C)

master:

1 2 3 4 (6P4C)

remote:

1 2 3 4 (6P4C)

master:

1 2 (6P2C)

remote:

1 2 (6P2C)

Open circuit: wire 2 is broken,

indicator 2 does not light up on

master and remote.

master:

1

2

3 4 5 6 7 8

remote:

1

2

3 4 5 6 7 8

Open circuits: wires 2 and 5

are broken, indicators 2 and 5

do not light up on master and

remote.

Note: If less than two wires in

the cable are connected, none

of the indicators lights up.