Banks Power Dodge Trucks: (Diesel ’03 - 07 5.9L Cummins) Intake- High-Ram Air Intake '03-07 User Manual

Page 9

Advertising
background image

96768 v.8.0

9

14.

Slide the second provided intake

gasket over the four studs and set the

High-Ram in place on the studs. Twist

a Stat-o-seal washer over the inner

two studs, then over each stud install

a flat

5

16

” AN washer. Install a

5

16

-24

nylock nut on each stud and tighten all

four evenly between 140 to 150 lb-in.

See Figure 5.
CAuTION: use only handtools when

tightening the High-Ram. Tighten

snugly but do not overtighten.

Damage to the High-Ram casting

can result from the use of

pneumatic tools or excessive

tightening.

15.

Place the supplied spacer on

the stud on the High-Ram. Mount the

bracket on the MAP and FRP wire

harness to the stud, and secure the

bracket with the original washer and

nut that were removed in Step 3.

16.

The plastic pin on the heater wire

harness will not be used to secure to

the High-ram. Use a supplied cable tie

to secure the harness away from any

heat source.
NOTE: Before slipping any boost tubes

and the corresponding hoses, into

position, ensure that all connection

ends are clean and free of any oil

residue and contaminates. Clean

compressor outlet and all connection

points with a non-oil based solvent

such as Acetone, Mineral Spirits,

Denatured Alcohol or Lacquer Thinner.

Read and follow the manufactures

operation instruction for non-oil based

solvent cleaner.

Figure 6

Advertising