Banks Power Dodge Trucks: (Diesel ’07 - 12 6.7L Cummins) Exhaust- Monster Exhaust, Split-Dual, side exits '07-10 including Mega Cab User Manual
Page 8
8
96466 v.7.0
9.
Install the Banks hanger bracket
onto the rear of the driver-side frame
rail. Behind the rear shock cross
member, place the hanger bracket
over the frame rail on the inside. Align
the hole in the center of the frame
with the hanger bracket. Install the
7
⁄
16
”x 4” & washer through the bracket
and frame rail. Secure the bolt on the
outside frame rail using the 2”x 2”
plate, washer and
7
⁄
16
” nut. Be sure
the hanger pin is parallel with the
frame rail and torque
7
⁄
16
” hardware to
48 ft-lb (see Figure 5).
10.
Install the supplied rubber
insulator onto the Banks hanger
bracket.
11.
Install the driver-side tailpipe
into the top Y-pipe outlet. Install the
driver-side tailpipe hanger into the
vehicle rubber insulator. See Figure 6.
12.
Install the passenger-side tailpipe
into the lower Y-pipe outlet. Install the
passenger-side tailpipe hanger into the
vehicle rubber insulator. See Figure 3.
13.
Move the spare-tire to the rear
of the vehicle and center between the
dual tailpipes. Tighten the spare tire
with the manufacture tire tool so that
it is retained into place (See Figure 7).
DRIVER SIDE
TAILPIPE
PASSENGER
SIDE
TAILPIPE
3.5”
CLAMP
REAR
HANGER CLAMP
FORWARD
4“
CLAMP
Y-PIPE
INTERMEDIATE
PIPE
Figure 4