1.

Disconnect the negative

(ground) cable from the battery (if

there is more than one battery,

disconnect both negative cables).

Secure the cable so it cannot

accidentally come in contact with the

post.

2.

Raise the vehicle and support it

securely with properly weight-rated

safety stands, ramps or a commercial

hoist. Take care to balance the vehicle

to prevent it from slipping or falling.

When using ramps, be sure the wheels

are centered squarely on the topsides.

Place the transmission in park

(automatic) or reverse (manual), set

the parking brake and securely block

the wheels that are on the ground.
CauTIoN: Do NoT WoRK uNDER

aNY VEHICLE SuPPoRTED oNLY

BY a FLooR JaCK. SEVERE INJuRY

MaY RESuLT.
WaRNING! The following step may

require the use of a torch and/

or saw. Proper safety equipment

should be used. Failure to use

proper safety equipment may

result in severe injury.

3.

From under the vehicle remove the

factory exhaust starting at the rear of

the muffler. Remove the tailpipe by

removing the two (2) nuts connecting

the muffler to the tailpipe. Remove

and retain the two (2) M8x1.25 bolts

retaining the rubber hanger on the

rear tailpipe hanger. Remove and

retain the rubber hanger. Remove the

tailpipe assembly from the vehicle

(See Figure 2).

4.

Remove the muffler and y-pipe

assembly by removing the four (4)

M8x1.25 nuts from the studs of the

two (2) flanges after the 3rd and 4th

catalytic converters. Retain these four

(4) nuts for reassembly (see Figure 3).

5.

Remove and retain the two

M8x1.25” factory bolts holding the

factory y-pipe rubber hanger and

detach the rubber hanger. Remove the

y-pipe and muffler assembly.

6.

Align the factory rubber hanger

onto the Banks hanger plate and

secure with the supplied

5

16

” bolts,

nuts and washers (see Figure 4a).

7.

Align the hanger plate assembly

onto the original location of the hanger

such that the rubber hanger is on top

of the plate. Loosely reinstall the two

(2) factory bolts through hanger plate

into the vehicle frame.

8.

Install the two (2) gaskets onto the

right and left side catalytic converter

flanges. Install the y-pipe flange onto

the right side catalytic converter

flange. Lightly tighten the factory two

(2) M8x1.25 onto the factory studs.

9.

Install a 3” clamp onto the left side

headpipe outlet. Install the headpipe

slip fitting onto the y-pipe assembly.

Install the headpipe flange onto the

left side catalytic converter flange.

Reinstall the ground strap onto the

right factory stud and lightly tighten

the two (2) factory M8x1.25 onto the

factory studs (see Figure 3).

10.

Install the supplied 3” Hanger

clamp into the inlet of the Intermediate

pipe extension. Start the hanger clamp

pin into the corresponding vehicle

rubber hanger. Install the extension

pipe onto the y-pipe assembly. Lightly

tighten the hanger clamp.

11.

Install a 3” clamp onto the inlet

of the Banks Muffler. Install the Banks

Muffler onto the y-pipe assembly or

extension pipe. Verify the Muffler

inlet is connected to the y-pipe or

extension pipe.