Grain Systems PNEG-102 User Manual
18" full floor transition, Diagram a: as viewed from inside bin
Advertising
12-18" FULL FLOOR TRANSITION
Field drill bolt holes into sidewall
sheet for entrance collar sides and
sizing angle. Completely seal all
possible spots for water and air leak-
age with the provided tube caulking.
the diagram showing the 1" dimen-
sion from bottom of entrance collar
side bracket to concrete. This di-
mension is important for proper fit
of transition.
When installing the GSI aeration
transition, it will be necessary to field
cut a hole into the bottom sidewall
ring. Refer to diagram A for proper
dimensions of cutout. Take note of
Note: Entrance collar
side bracket (TR-4731)
flange must be in-
stalled to the inside of
the bin sidewall.
DIAGRAM A: AS VIEWED FROM INSIDE BIN