5. Slide & insert the switch assembly to engage
the cassette side sheet in the slot and push 
towards the front as shown in Fig. 2 
Table 3: Switch terminals for cat GCPS1R
Breaker Position
Continuity between 
terminals 
Disconnected D11-D14 
Test D31-D34 
Connected D51-D54 
 
 
Table 4: Switch terminals for cat GCPS2R 
Breaker Position
Continuity between 
terminals 
Disconnected D11-D14
&
D21-D24
Test D31-D34
&
D41-D44
Connected D51-D54
&
D61-D64
Figure 2. CPS assembly.
6. Push the complete assembly to come out side
of the cassette and the snap feature engages 
with the cassette side sheet as shown in Fig.3. 
 
 
 
 
 
 
 
 
 
 
 
Figure 3. CPS assembly
7. Ensure the assembly is firmly fitted and locked
down by the four snaps features.
 
 
8. Check functionality of carriage position switch
by racking in the breaker and racking out the 
breaker and confirming changeover of switch 
as specified in table 3 & 4. 
 
 
 
9. Complete the wiring with the equipment.