Installation, Caution – Xylem MM 200G Series 64 Low water Cut-Offs User Manual

Page 3

Advertising
background image

3

a. The line on the casting of the model 64 must be installed above the lowest permissible water level

determined by the boiler manufacturer.

a. Study the figures to the right and determine which

figure shows how the 64 control will be attached to

the boiler.
Figure 1. Connect the upper equalizing pipe to

the riser going to the radiation or to the compression

tank. Connect the lower equalizing pipe to any

available opening in the side of the boiler.

NOTE: If

no opening is available in the side of the boiler,

connect the lower equalizing pipe into the drain

connection.
Figure 2. If there is a tapping available on the

top of the boiler connect the upper equalizing pipe to

it.

NOTE: During initial filling or after blow down the

upper equalizing pipe and possibly the 64 control will

have an air pocket. Connect a vent or bleed valve on

the top of the vertical equalizing pipe. If the Test-N-

Check (TC-4) valve is used the vacuum breaker can

be used to bleed the air pocket.

CAUTION: When bleeding an air pocket manually,

protect yourself from being burned with hot water.
Figure 3. If there is no tapping available on the

boiler, connect both the upper and lower equalizing

pipe into the vertical riser going to the radiation or to

the compression tank.

IMPORTANT: The horizontal

equalizing pipe should not be above the horizontal

run going to the radiation. If it is, an air pocket will be

created and a vent or bleed will have to be installed.

STEP 2 - Installation of the Model 64

Model 64 – For Hot Water Boilers with 1" (25mm) Equalizing Lines

INSTALLATION –

TOOLS NEEDED:
One (1) flathead screwdriver and two (2) pipe wrenches.

For float type controls it is recommended that Test-N-Check

®

(TC-4) valves be used in the upper and

lower equalizing lines. They offer a functional means for testing the 64 control, and conform to the

ASME CSD-1 code.

STEP 1 - Determine the Location of the Low Water Cut-Off

VERTICAL RISER
TO RADIATION

HOT WATER

BOILER

MODEL

64

VERTICAL RISER TO RADIATION
OR COMPRESSION TANK

HOT WATER
BOILER

TC-4

TC-4

MODEL

64

HOT WATER
BOILER

AVAILABLE OPENING
IN TOP BOILER

AIR
VENT

MODEL

64

Figure 1

Figure 2

Figure 3

Test the Model 64 Before Leaving the Site

While the burner is operating open the blow-down valve, causing the water level to drop in the float chamber. As

the float drops the alarm circuit (if used) closes first; then on further drop the cut-off circuit will open, shutting the

burner off.

NOTE: If no Test-N-Checks (TC-4) valves were used, do this test before filling the system completely.

IMPORTANT: Instruct boiler attendant to blow down the float chamber at least once a week during the heating

season, if operating pressure is below 15 psi (1 kg/cm

2

). If above 15 psi blow down once a day.

NOTE: On a new boiler installation, leaky system, or where the quality of the water is poor, blow down the control

more frequently.

Protect yourself when blowing down controls, hot water will flow out of the drain pipe attached to the blow-down valve.

Failure to follow this caution may result in serious burns.

CAUTION

Advertising