MAINTENANCE

SCHEDULE:

• Blow down control as follows when boiler is

in operation.
– Daily if operating pressure is above 15 psi (1 bar)
– Weekly if operating pressure is below 15 psi (1 bar)

NOTE: More frequent blow-down may be neces-

sary due to dirty boiler water and/or local codes.
• Remove and inspect probes annually.
Replace

probes if they are worn, corroded or have an
excessive coating of scale or rust.

• Inspect the chamber and equalizing piping

annually. Remove all sediment and debris.

When blowing down a control at pressure, the blow
down valve should be opened slowly. The piping
needs to be warmed up and stagnant water in the
drain piping needs to be pushed out. Suddenly
opening a blow down valve causes steam to con-
dense, which creates water hammer. Damage to
components can occur when water hammer occurs
due to improper blow down piping.

For these reasons, McDonnell & Miller recommends
a dual valve blow-down system for each control.

Proper Blow-down Procedure:

(Using dual valve system)
1. With water in the boiler at its normal level, open

“Positive Shut-off Ball Valve”.

2. Open “Throttling Gate Valve” slowly until drain

piping heats up and then open fully. Observe that
the water level starts falling in the gauge glass.

3. Close “Throttling Gate Valve” after verifying that

the pump contacts have closed and the burner
contacts have opened thus shutting down the boiler.
Note: If this does not happen, immediately close
all valves, turn off burner and correct the problem.

4. Close “Positive Shut-off Ball Valve”.

5. Observe that the water level returns to its normal

level before leaving site.

DUAL
VALVES
FOR
BLOW
DOWN

BALL VALVE

GATE VALVE

To prevent serious personal injury from steam

pipe blow down, connect a drain pipe to the

control opening to avoid exposure to steam

discharge.
Failure to follow this caution could cause

personal injury.

!

CAUTION

Replace probe every 10 years. More frequent

used in locales

required, or in appli-

replacement of the probe is required if it is

significant water treatment is

high make-up water requirements.

!

CAUTION

!

CAUTION

Replace Probe if:

!

NOTE

Clean probe by wiping with non-abrasive cloth and
rinsing with clean water.DO NOT use sharp instruments

to remove any accumulations of rust or scale.

PFA insulator is cracked or worn.
Probe is loose.Failure to follow this caution could

cause property damage,personal injury or death.


Replace the control every 15 years.