Elmo Rietschle V-VCB 20/25 User Manual

Page 14

Advertising
background image

14

|

www.gd-elmorietschle.com © Gardner Denver Schopfheim GmbH, Gardner Denver Deutschland GmbH

Installation

5 Installation

5.1

Preparing for installation

Check the following points:

Machine freely accessible from all sides

Do not close ventilation grids and holes

Suffi cient room for installing and removing pipes
and for maintenance work, particularly for install-
ing and dismantling the machine

No external vibration effects

Do not suck any hot exhaust air from other ma-
chines into the cooling system.

The oil fi lling pointFig. 2/H), oil sight glassFig. 2/I) and oil outletFig. 2/K) must be easily accessible.
The cooling air inlets (Fig. 2/E) and the cooling air outlets (Fig. 2/F) must be at least 15 cm away
from adjacent walls. Discharged cooling air must not be sucked in again.For maintenance work
there must be a space of at least 30 cm around the machine.

5.2 Installation

NOTICE

The machine may only be operated when it is
set up horizontally.

Material damage resulting from the machine
tipping over and falling.

When installed at more than 1000 m above sea
level a reduction in power is noticeable. In this
case we would ask you to contact us.

Ensure that the foundation complies with the follow-
ing conditions:

Level and straight

The bearing surface must be at least the same
size as the machine

The bearing surface must be able to bear the
weight of the machine

It is possible to install the machine on a fi rm base without anchoring. When installing on a substruc-
ture we recommend fi xing with fl exible buffers

Advertising