Commissioning and decommissioning

6.1.1 Checking the rotation direction

The intended direction of rotation of the drive

shaft is shown by the rotary direction arrow on
the inlet ring.

a) Start the motor briefl y (max. two seconds) to

check the direction of rotation. To see the direc-
tion of rotation using the aperture on the inlet
ring. For this the fi lter housing (Fig. 2/h

2

) must

be removed. Remove clips (Fig. 2/y

2

), remove

fi lter cover (Fig. 2/e

2

) complete with fi lter housing

(Fig. 2/h

1

) and the fi lter insert (Fig. 4/f

2

). When

looking at the impeller, it must rotate clockwise.

NOTICE

Incorrect direction of rotation
Running in reverse for a long time may damage the
machine.
Use a phase sequence indicator to check the direc-
tion of rotation (anti-clockwise rotating fi eld).

6.2 Decommissioning/

storing

Stop the machine

a) Switch the machine off.

b) If available close the cut off device in the suction

pipe.

c) Disconnect the machine from the electricity

source.

d) Depressurise the machine: Open the pipes

slowly.

The pressure reduces slowly.

e) Remove the pipes and hoses.

f) Seal the connections for suction nozzles using

adhesive foil.

see also Section 3.2.1, Page 11

6.3 Re-commissioning

a) Check the condition of the machine (cleanliness,

cabling etc.).

For installation see Section 5 Page 14

For commissioning see Section 6.1 Page 16