4. Commissioning and ignition

4 Commissioning and ignition

4.1 Commissioning



Initial commissioning must be done by a qualified
professional.

1. Check the water pressure in the installation. Top up with more

water if necessary.

3. Carry out the boiler ignition operations (See chapter: Ignition -

CBB 20).

4. Set the output modulator to 80°C.

5. Open the air regulator flap by tensing the chain and wait for the

thermometer to reach 80°C.

6. Secure the chain to obtain an opening of 5 mm and mark the link.



Check that the air regulator flap is fully closed if the boiler
reaches 90°C.