4.

Place the saddle brackets onto the U-Bolts on the axle tubes. Place the U-Plates over the D shaped bushings on the bar
and attach the bar to the U-Bolts and saddle brackets with the flat washers and nuts provided.

LEAVE LOOSE AT

THIS TIME to allow for adjustment later.

6.

Position sway bar on axle so that it clears all frame mounted components including fuel tanks, brake lines, fuel lines, etc.
Sway bar can be rotated back and forth on axle to maximize clearance.

7.

Assemble end links by inserting bushings and inner sleeve into outer sleeve of end link.

Fully lubricate bushings be-

fore installation.

8.

Attach end links to the outer hole of the sway bar and align end links for best fit as shown in PHOTO 4.

9.

The end links should be located as shown in PHOTO 4 so that the arms of the sway bar are parallel with the ground.
When satisfied with their location, mark location of holes for the end links.

10. Prepare to jack up vehicle by placing wheel chocks on the front wheels. After the rear of the vehicle has been raised,

support frame on jack stands and remove rear wheels.

11. Transfer hole location to outer edge of subframe rail. A piece of card board can be used by marking the location of the

hole on the cardboard and transferring the location to the outer rail. Drawing a line on the subframe square to the sub-
frame rails will keep the hole location square. See PHOTO 5,6&7.

12.

Review end link mounting detail before drilling holes. BEFORE DRILLING ANY HOLES IN THE RAIL—

RELOCATE AND PROTECT ANY FUEL OR BRAKE LINES THAT MAY INTERFERE WITH THE DRILL

BIT OR SWAY BAR INSTALLATION.

13. Drill a 15/32 (.468) hole through

BOTH walls of the subframe. Make sure holes are square to one another when drilling

holes.

14. Drill an 11/16 (.688) hole through

OUTER wall of subframe ONLY.

15. Insert 7/16 X 4-1/2 bolt through rail as shown in PHOTO 8. Insert 1.720” long spacer sleeve into hole so that it is flush

with the inboard wall of subframe. For severe duty it is recommended that the spacer tube be welded to the outer sub-
frame wall.

If the spacer is to be welded, review severe service end link detail on page 4 and skip to line 17. If any

welding is to be done, the installer must ensure that all hazards (fuel, electrical, etc) are eliminated and that fuel

tanks, fuel lines, brake lines, wiring, etc. are not affected by the welding operation.

16. Install Large washer over spacer tube and check that spacer tube is at least 1/32” below the surface of large washer.

Failure to do this will result in insufficient preload and noise. File or grind end of spacer tube to achieve proper length.
SEE PHOTO 9.

17. Remove bolt and spacer and attach end link to subframe as shown in detail and PHOTO 10. Applications with welded

spacer do not require the washers on the outboard side of subframe. Torque end link bolts to 35-40 ft-lb.

18. Replace rear wheels and torque lug nuts to factory specification. Lower vehicle so that the full weight of the vehicle is

on the suspension.

19. Tighten axle u-bolts to 35 ft-lb.