Installation, Important, Prepare pit – Poweramp CM SERIES MECHANICAL User Manual

Page 11

Advertising
background image

9

4111-0006 — Sept 2010

Sept 2012

INSTALLATION

Prepare Pit

1. Before lowering the dock leveler into the pit, the

following must be performed:

2. Remove all debris from the pit and sweep the pit

clean.

3. Check the entire dock leveler pit for proper

construction according to approved/certified pit
drawings. Make sure pit is square by making the
following measurements:

• Measure pit width distance (A) at both front and

rear of pit.

• Measure dock floor-to-pit floor distance (B) at all

four corners.

• Measure pit length distance (C) at both sides.
• Measure corner-to-corner (criss-cross) distance

(D) at both sides. Take measurements at dock
floor level and at pit floor level.

4. If any measurement is off by more than 1/8 in.

(3.18 mm), contact Poweramp Technical Services
before proceeding.

A— Distance (Pit Width)

(Front and Rear)

B — Distance (Dock Floor-to-Pit

Floor) (All Four Corners)

C — Distance (Pit Length)

(Both Sides of Pit)

D — Distance (Pit Corner-to-Corner)

(Top, Bottom, and Both Sides)

IMPORTANT

DO NOT remove the shipping bands around the
dock leveler lip until instructed to do so.

Post safety warnings and barricade the work area at
dock level and ground level to prevent unauthorized
use of the dock leveler before installation has been
completed.

Failure to follow the installation instructions can
result in damage to dock leveler, the facilities, and/
or serious personal injury or death.

Only trained installation professionals with the
proper equipment should install this product.

B

D

C

A