Installation, Install control panel and wiring – Poweramp HED SERIES HYDRAULIC User Manual

Page 28

Advertising
background image

26

Manual No. 4111-0027

Sept. 2009

May 2012

26

1. Mount the push-button control panel (B) so bottom

of control panel-to-dock floor distance (C) is 48 in.

(1219.2 mm).

2. Install electrical disconnect panel (A) if not already

installed.

3. Install and connect the control wiring.

4. Connect the dock leveler power cable to the field

wires in the pit junction box. Refer to the electrical

drawings supplied with the dock leveler.

5. After all electrical connections have been made,

disengage the maintenance prop and lower the

platform using the external lifting device connected

to the platform lifting brackets.

A— Disconnect Panel

B— Control Panel

(provided by others)

C— Distance, 48 in. (14 630 mm)

The electrical power must be OFF prior to electrical

installation. For maximum protection, use an OSHA

approved locking device to lock out all power

sources. Only the person installing the equipment

should have the key to unlock the power source.

Failure to follow these instructions may result in

serious personal injury or death.

DO NOT make any final electrical connections until

all welding has been completed. Failure to do this

may result in serious personal injury or death.

All electrical work — including the installation of

the disconnect panel, control panel, and final

connections to the pit junction box — must be

performed by a certified electrician and conform to

all local and applicable national codes.

Always stand clear of platform lip when working in

front of the dock leveler. Serious personal injury or

death may result.

Install Control Panel and Wiring

INSTALLATION

B

A

C

Center Line

(CL)

30” off CL