2.2 Fully raise lift. Inspect sheaves (pulleys) in runway ends with lift in raised position.

a. Visually inspect alignment of sheaves, see figure above. Misalignment of sheave(s) indicates

excessive wear; the sheave(s) and sheave pin should be removed and inspected. Replace as

required.

b. Hold lowering handle down to lower lift onto latches. Pull on cables under runway to create cable

slack.

c. Check for excessive side to side wobble. Grasp rim of sheave and attempt to wobble (tilt) side to side,

refer to figures above. If sheaves wobble (tilt) more than 1/16” (1.6 mm) side to side, or move in and

out more than 1/32” (0.8 mm), the sheave and sheave pin (shaft) should be replaced, refer to figures

above.

3. Hydraulic Cylinder

Inspect the hydraulic cylinder mounting to the runway. Inspect cylinder and hydraulic hoses for leaks. Repair or

replace as required.