3.2.5. Wiring the Junction Box
Load Cells are preinstalled, plumbed, and pre-wired to the Junction Box at the
factory, prior to shipping.
─ Dip Switches are not set.
─ Interconnecting cables are not installed.
1. Open the platform access cover, then the junction box cover.
2. Loosen all gland bushing nuts.
3. Wire the Indicator to Junction Box according to the chart below.
4. Follow the indicator installation manual to properly connect it with the platform.
5. Tighten all gland bushing nuts.
IMPORTANT NOTE:
Leave the Junction Box Cover off until all corner
adjustments are completed.
WIRE COLOR
FUNCTION
Red
(
−) Signal
White
(+) Signal
Black
(
−) Excitation
Green
(+) Excitation
Yellow
Ground