Installation, Basic assembly steps – Fairbanks 9102 FB Omnicell User Manual

Page 12

Advertising
background image

Section 2: Installation

10/07

12

51175 Rev. 3

INSTALLATION

Basic Assembly Steps

1. Raise the vessel that is to be supported by the Omnicell

®

Assemblies.

2. Secure the Assembly by safely placing blocks under the vessel to the required

height.

3. Place each Assembly onto a level surface under each support leg.
4. Set the Assemblies for the correct load cell orientation (as shown on the

following page

).

5. Insert the four (4) bolts, and then fasten them loosely to the support leg for

each assembly.
1/2-13 bolts for 5,000 lbs. capacity and under
5/8-11 bolts for 10,000 lb capacities.

6. Mark the location of the anchor bolt locations.
7. Slide the assembly back and drill the anchor hole locations.
8. Re-position the load cell assemblies, level, and anchor all assemblies.
9. Lower the vessel onto the top plate of each Omnicell

®

Assembly.

10. Tighten the bolts, securing the load plates to each support leg of the vessel.
11. Remove all cribbing blocks.
12. Route the cables to the junction box and indicator.
13. Wire the Omnicell

®

Assemblies

according to the appropriate junction box and

indicator service manual.

Before the installation is considered complete, the equipment is to
be configured to meet or exceed any applicable weights and
measures requirements.

Advertising