22.5. SYSTEM CHARGING

22.6. SYSTEM DRAINING

Before commencing the charging procedure position

the main isolator of the unit in the OFF position.

1. Ensure that the system drain valve is closed

2. Open all the system air vents and of the terminal

units

3. Open the system isolating valves

4. Start filling slowly opening the system water

charging valve external to the unit

5. When water exits the terminal units air vents

close them and continue charging until the

required system operating pressure is reached.

1. Before commencing draining the draining proce-

dure position the main isolator of the unit in the

OFF position

2. Ensure the system water charging valve is closed

3. Open the system drain valve external to the unit

and all the system air vents and of the terminal

units.

WARNING

Confirm the hydraulic integrity of the

joints.

WARNING

It is recommended to repeat this pro-

cedure after the unit has operated for

a few hours and to periodically check

the system pressure. Charging to be

done with unit off (pump OFF).