MGE™ Galaxy™ 300 10-40 kVA 3:3, 10-30 kVA 3:1 - 380/400/415 V Installation

8

Connect the Battery Cables between the UPS and

Battery Enclosure

Warning: This procedure describes how to connect the initial battery cables between
the UPS and XR before start-up. If the UPS is up running, see “Connect an XR Battery
Enclosure to a running UPS” on page 10.

BAT+, BAT-, and N

1. Run the ground cable up

through the bottom front hole of
the XR and connect it to the
busbar.

2. Run the BAT+, N, and BAT-

cables up through the bottom
front hole.

3. Attach the cables to the right

side of the battery breaker.

4. Reinstall the side panels.

+

N

-

+

N

-

Front view

Cables to/from the UPS

Battery

enclosure