Appendix g-3 commissioning qa checklist – AOC 15 User Manual
Page 162

Appendix G-3 Commissioning QA Checklist
NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer on page v of
this document.
DOC012R02 AOC 15/50 User Manual Nov 2001
154
AOC 15/50 Commissioning Test QA Checklist
T u r b i n e N u m b e r
C u s t o m e r
Control Box Check
Q A C h e c k
Date
Inspect cabling to control boxes
Emergency Stop
Q A C h e c k
Date
Confirm function of Emergency Stop switch (MCR disabled)
Parking Brake release
Q A C h e c k
Date
Confirm electrical release of Parking Brake
(Rotor should turn if wind present)
NOTE: Parking brake release should produce an audible click
Anemometer Signal Check
Q A C h e c k
Date
W ith computer interface, check for signal from both units
( 0 - 5 V = 0 - 1 0 0 m p h )
Conduct Rotor Jog
Confirm Directional Rotation
Confirm RPM (50Hz 1495-1530 and 60Hz 1790-1830)
Q A C h e c k
Date
Confirm tip brakes do not deploy
Dynamic Brake Test
Check connection of 1M and 4M wires (control wires)
Observe sufficient drop in RPM
Q A C h e c k
Date
(33-50% drop without tip brakes or parking brake deployed)
C A U T I O N : D O N O T R U N D Y N A M I C B R A K E F O R L O N G E R T H A N T E N ( 1 0 ) S E C O N D S .
A L L O W R E S I S T O R S T O C O O L T O R O O M T E M P E R A T U R E B E F O R E R E P E A T I N G T E S T
Placing Turbine On Line
Q A C h e c k
Date
Observe turbine coming on line
Manual Shutdown
Confirm turbine coming off line
Q A C h e c k
Date
Turn turbine power switch to "OFF"
L o w W i n d S h u t d o w n
Q A C h e c k
Date
Observe low-wind shutdown.
(If conditions do not permit, simulate electrically)
QA Approval Signature
Date