4.0 Planning and Installation Checklist

NOTICE: Use of the material contained in this document is subject to the warning on page Iv and the disclaimer

on page v of this document.


DOC012R02 AOC 15/50 User Manual Nov 2001

29

Day 1:

•

Plan and prepare erection

•

Assemble tower

•

Test generator and use it as a motor to test drive train

•

Clean blades and install tip brake cable

•

Prepare tip brake studs and cavity

•

Prepare blade bolt inserts

•

Attach twist cable

•

Install two of three blades if time permits (fork lift, boom truck, etc.)


Day 2:

•

Lift and install tower on foundation (crane)

•

Install blades on hub

•

Install tip brakes on blade ends

•

Lift and mount machine onto the tower

•

Torque tower top fasteners

•

Torque all tower bolts and add pal nuts


Day 3:

•

Install and wire anemometers

•

Wire twist cable junction box and disconnect (if applicable) at tower base

•

Grout tower legs

•

Mount warning signs as required

•

Troubleshoot and commission


Day 4:

•

Complete any further installation details

•

Carry out final QA check

•

Monitor performance (wind permitting)