Replacing VC modules

Replacing VC modules in a VC Domain managed by VCEM

To replace a VC Ethernet module or a VC Fibre Channel module of a VC Domain managed by
VCEM, perform the following:
1.

From the VCEM home page, click the VC Domains tab.

2.

Select the VC Domain with the VC modules to be replaced.

3.

Click Remove from VC Domain Group. Wait for the job to complete successfully.

4.

Replace the VC modules from the enclosure rear interconnect bays. Verify that the network
and SAN connections that are wired to the new VC modules are the same as the old
connections.

5.

If the primary VC Ethernet module was replaced, then you must configure the VC Domain
again through VC. For more information about configuring the VC Domain, see the HP Virtual
Connect For c-Class BladeSystem User Guide
.

6.

Access the Onboard Administrator web interface for the enclosure to verify that the VC Domain
link in the bottom left portion of the screen correctly points to the VC Domain Manager IP
address.

7.

Perform an Systems Insight Manager discovery against the Onboard Administrator IP address.

8.

From the VCEM home page, click the VC Domains tab.

9.

Select the same VC Domain, and then click Add to VC Domain Group. Wait for the job to
complete successfully.

Verify that the VC Domain meets the requirements for adding a VC Domain to a VC Domain
Group.

For more information, see

“Requirements for adding a VC Domain to a VC Domain Group”

(page 25)

.

Replacing VC modules in interconnect bays three to eight in a VC Domain Managed
by VCEM without removing the VC Domain from the VC Domain Group

Perform the following steps to replace a VC Ethernet module or a VC Fibre Channel module in
interconnect bays three to eight of a VC Domain managed by VCEM without removing the VC
Domain from the VC Domain Group:
1.

Ensure that the VC Domain Group has only one VC Domain.

2.

Click VC Domains from the VCEM home page

3.

Select the VC Domain with the VC modules to be replaced.

NOTE:

The modules to be replaced cannot be primary or secondary modules (usually

interconnect bays one and two) and the modules must have the same model.

4.

Click VC Domain Maintenance... and then click Make Changes via VC Manager….

5.

Replace the VC modules in the enclosure rear interconnect bays. Verify that the network and
SAN connections wired to the new VC modules are the same as the old connections.

6.

Use the VCSU to update the Virtual Connect firmware using the same firmware version that
was previous installed on the replaced modules to make sure the new modules have the same
firmware version.

7.

In the VCEM GUI click Complete VC Domain Maintenance. Wait for the job to complete
successfully

For specific information on how to use FlexFabric modules, see

“Using FlexFabric modules”