Installation

20

900-0113-01-00 Rev A

Mounting Surface

M8 x 1.25 Stud

Lock Washer

Battery

Cable Lug

13 mm Nut

Flat Washer

Insulator

Install battery cable lug, nuts and washers in the
order illustrated. The battery cable lug should be the
first item installed on the stud. It should make solid
contact with the mounting surface. Do not install
hardware in a different order than shown.

Figure 9

Required Order of Battery Cable Hardware

CAUTION: Fire Hazard

Never install extra washers or hardware between the mounting surface and the
battery cable lug. The decreased surface area can build up heat.