Vertical contact toaster, Troubleshooting (continued) – A.J. Antunes & Co VCT-20 9200560 User Manual

Page 14

Advertising
background image

VERTICAL CONTACT TOASTER

14

P/N 1010729 Rev. G 09/13

Problem

Possible Cause

Corrective Action

Platen is hot and the Conveyor

Belt chains are not rotating.

Toaster is installed incorrectly. Refer to the Installation and Operation sec-

tions of this manual for proper installation and

operating procedures.

Wiring problems.

Check all electrical connections for burns,

discoloration or arcing. Replace all connec-

tions or components with damaged terminals.

Replace all damaged wiring with the same (or

higher) rated wire.

Drive motor inoperable or

incorrect conveyor drive

motor.

To check drive motor:
1. Measure resistance of motor coil. Replace

motor if coil measures either open circuit or

zero resistance.

2. Mark the drive motor sprocket and count

the turns per minute. Correct drive motor

speed is nine (9) turns per minute for VCT-

20; three (3) turns per minute for VCT-25;

one (1) turn per minute for VCT-50.

Broken Drive Chain or loose
sprocket.

Check the Drive Chain for kinks, broken or

bent links, or other damage. Check the motor

sprocket and drive sprockets (on drive shaft);

tighten setscrew on flat of shaft if required.

Check for damaged/worn sprockets and

replace as required.

Heat Shield not installed or

installed incorrectly.

Install the Heat Shield so that it activates the

Conveyor Interlock Safety Switch.

Conveyor Belt chains

installed incorrectly.

Install the Conveyor Belt chains according to

the Maintenance Section of this manual. Be

sure that ends of the hooks are facing down.

Conveyor Interlock Safety

Switch is not activated.

Install the Heat Shield so that it activates the

Conveyor Interlock Safety Switch.

Spring Tensioner Assembly or

Tensioner bent or missing.

Replace the Spring Tensioner assembly(s)

(item 29, page 22) or Tensioners (item 4, page

24) if damaged or loose. Replace the Slide

Rails (item 40, page 24) if worn or missing.

Conveyor Belt chains too

loose or missing links (41

links required when new).

When new, conveyor has 37

large links and 4 small links.

Adjust or replace the Conveyor Belt chains

according to the Maintenance section of this

manual.

TROUBLESHOOTING (continued)

Advertising