NaceCare Solutions ST732 User Manual

Page 8

Advertising
background image

7

MACHINE PREPARATION

3. BATTERY INSTALLATION

The batteries must be fitted in the compartment under the recovery tank and
must be handled by using appropriate lifting equipment suitable both for the
weight and for the lifting system.

ATTENTION! When recharging the batteries be sure to follow the
manufacturer’s specifications.
Only trained staff may carry out the installation and maintenance
procedures. Please ensure all proper safety equipment is used
while installing or maintaining the batteries.

For the battery installation it is necessary to:
1. Lift the cover of the recovery tank (1)
2. Take off the suction cover (2) rotating it counter-clockwise
3. Lift the recovery tank from the side.

2

4. Make sure that the drainage hole placed on the bottom of the battery tray is

not covered.

5. Place the batteries inside the compartment
6. If the batteries are already charged, the machine connector can be

assembled to the battery connector. Otherwise proceed with the charging
process as indicated below

7. Reassemble the machine

4. CONNECTING THE BATTERY CHARGER

The connector for the battery charger is delivered with the machine and can
be found in the bag where this instruction booklet is found. It must be
assembled on the battery charger cables following the battery chargers
instructions

ATTENTION! This operation has to be carried out by trained
staff. A wrong or incomplete cable connection to the connector
can cause serious damage to persons, the electrical system of
the machine, and the batteries.

Advertising
This manual is related to the following products: